|
I know the previous holes were roughly 700m and less. I think the 8000m is combined. But I could be wrong I'm not a mining expert.
I found a company in Chile's estimated drilling costs.
Budgeted cost for mapping and 8,000m drill program:
Camp Labour $ 8,200
Assaying (8,000 samples & $15) $120,000
Drilling (8,000m)
Diamond drilling:4,800m@$95/m $456,000
RC drilling: 3,200m@$50/m $160,000
Equipment (Bulldozers & truck rentals) $198,000
Food & Supplies $ 31,000
Geologists (Project Mngr. + 3 geologists) $291,000
Transportation $ 18,200
Contingency $ 10,000
Total: US$1,292,400
__________________
They/them
69 Camaro LS/T56
|