Of course it being Christmas vacation I had to get more done since I want the cabinets installed the second or 3rd week of Jan.
Electrical is almost complete, inspection on Tuesday and then it will get finished off. We have about 10 plugs in the kitchen which will be perfect and needed.
Had a friend come over and helped me skim the ceiling and then put mud on it, he also helped move the far light closer and in line with the middle kitchen light (you can see how bad it was in a previous pic)
Really started in on the bathroom today, took out the inside wall since the electricians need to change the location of the fan switch which was next to the toilet (how fucken stupid) the floor is going to be horrible to remove which I'm so excited about...
Of course we found the particle board is rotten next to the tub, I'm so hoping the sub floor will be fine but we will be replacing the tub so it will be an easy fix if needed.